Road Paving Projects Rt. 49 & Tripoli Rd

Road Work Ahead

The State of New Hampshire will be repaving 9.2 miles of Route 49 (from Campton to the intersection of Tripoli Road) as well as 1.2 miles of Tripoli Road (from the Rt. 49 intersection to the split at the mountain access road). This is not a major construction project and will consist of applying a shim and overlay on the road surface. 

  • Route 49 Project Schedule:
    • Project Start – Tuesday, July 6 
    • Planned Project Duration – July 6 to August 2
    • Planned Paving Dates – July 19 to July 23
  • Tripoli Road Project Schedule:
    • Project Start – Friday, July 9 
    • Planned Project Duration – July 9 to August 5
    • Planned Paving Date – July 26